Inter Linking of Rivers from Cauvery to Agniyar using Construction Techniques

P. Jeyapushpa, P. Latha

Abstract :

This Project aims to give a detail about the Inter linking of rivers from Cauvery to Agniyar using construction techniques .In a canal alignment from Cauvery to Agniyar the total length of canal is 94.150 Km. This thesis analysis only taken for 16 km from Ls 78.050 to 94.150 km. In this canal Alignment from L.S 84.350 to 90.350 Km near Pudukottai District. The deep of cutting more than 30M to overcoming the complication. The deep cutting portion in the proposed link canal alignment by various methods is choosen and compared Open excavation, Cut and cover and Tunneling.